iPE Help

How is the Weighted Impact of a Risk Calculated

Updated on

Explains how weighted cost impact for a risk is calculated

Cost Impact & Probability

The weighted cost impact of a risk is, in basic terms, the probability of that risk occurring multiplied by the cost impact of that risk should it occur.  For example if there is a 10% chance that the project manager leaves the company part-way through the project and the cost impact of bringing a new project manager up to speed is $5,000 - then the weighted cost impact is $500.

The weighted cost impact of a risk is important because it is used to establish funds or reserves in the project to pay for the likelihood of some of the project risks occurring.

Influence of Risk Severity of Weighted Cost Impact

Depending on your risk policy, the weighted cost impact may take overall severity into consideration. If your risk policy incorporates severity into the weighted cost impact then the weighted cost impact is now the probability of the risk occurring multiplied by the cost impact of risk should it occur, multiplied by the overall severity of the risk.

Risk severity normally ranges from close to 100% (for significant or critical risks) down to 20% or less for smaller risks which do not impact performance or milestones visible to the end customer. Overall severity is like a fudge factor reducing the net weighted impact of a whole series of risks, as seen in the context of a competitive proposal.  Individual or larger risks have a higher severity - so less or no reduction in weighted cost impact - vs. smaller individual risks within larger groups of risks having a lower severity, because each risk on its own won't make much different to the overall program delivery cost.

The decision whether or not to consider overall severity is determined during the implementation with your consultant and pre-set on the risk-policy which is assigned to your project.

Adopting Target Cost Impact as Weighted Impact

Under certain conditions, such as during the release or completion of mitigation plan tasks, the target weighted cost impact is used in place of the initially assessed weighted cost impact for the risk. This is because a response to mitigate or control the risk is designed to reduce the cost impact or probability of the risk occurring, i.e. to reduce the weighted cost impact. This occurs either:

  • When a risk mitigation plan is released and the user selects the option to adopt the target weighted cost impact as weighted cost impact
  • When individual mitigation plan tasks are completed or marked as "done" and target probability or cost impacts were maintained for specific mitigation plan tasks
  • When the mitigation plan is completed (i.e. all the tasks are marked as done).

Please note that changes to the assessed probability, cost, schedule or performance impact in the ASSESSMENT tab after adopting the target weighted cost impact in this way will reset the weighted cost impact to the probability multiplied by the cost (optionally also multiplied by severity) again.

Previous Article How to Determine the Risk's Cost, Schedule or Performance Impact
Next Article How to Respond to a Risk